Labor and Equipment Requirements for 15-Acre Leyland Cypress Above-Ground
Container Nursery with 10-Acre Production Area, Climate Zones 8 and 9, 2000
Month Description Equipment Hours(Equipment) Hours(man)
Jan-Feb Prepare Greenhouse      
  Prepare Media 60 hp tractor 42 58
  Sterlize Greenhouse solo backpack 2 2
  Take cuttings hand tools 78 124
  Stick cuttings hand tools 38 41
  Cover greenhouse w plastic hand tools 6 6
  Mist until rooted mist system 219 5
Mar-Oct Check observe and water irrigation system 47 8
  Apply insecticide solo backpack 6 7
  Apply fungicide solo backpack 6 7
  Apply herbicide cylone spreader 13 14
  Fertilize hand tools 18 20
Nov-Dec Pruning hand tools 16 16
  Check observe and water irrigation system 32 10
 
Container Production
Mar Prepare Container Medium 60 hp tractor 120 135
  Step up into 3 gal hand tools 180 197
  Spray insecticide Air Blast Sprayer 10 10
  Apply herbicide cylone sprayer 6 7
  Apply fungicide solo backpack 6 7
  Fertilize hand tools 22 28
  Prune Shearing machine 190 210
  Hand Weed     90
  Apply Round Up around Beds solo backpack 5 6
  Check observe and Water irrigation system 304 214
Nov Shove plants up for wintering hand tools 18 20
Mar Prepare Container Medium 60 hp tractor 240 260
  Step into 10 gal hand tools 35 35
Mar-Nov Spray insecticide Air Blast Sprayer 10 10
  Apply herbicide cylone sprayer 6 7
  Apply fungicide solo backpack 6 7
  Fertilize hand tools 36 40
  Prune shearing machine 190 210
  Hand Weed     90
  Apply Round Up around Beds solo backpack 5 6
  Check observe and Water irrigation system 304 214
Mar Harvest   180 198